1630
Global
Height rank

Winthrop Center

Boston
Height 210.5 m / 691 ft
Floors 48
Official Name
The current legal building name.

Winthrop Center

Other Names
Other names the building has commonly been known as, including former names, common informal names, local names, etc.

Winthrop Square Tower, WSQ

Type
CTBUH collects data on two major types of tall structures: 'Buildings' and 'Telecommunications / Observation Towers.' A 'Building' is a structure where at least 50% of the height is occupied by usable floor area. A 'Telecommunications / Observation Tower' is a structure where less than 50% of the structure's height is occupied by usable floor area. Only 'Buildings' are eligible for the CTBUH 'Tallest Buildings' lists.

Building

Status
Completed
Architecturally Topped Out
Structurally Topped Out
Under Construction
Proposed
On Hold
Never Completed
Vision
Competition Entry
Canceled
Proposed Renovation
Under Renovation
Renovated
Under Demolition
Demolished

Completed

Completion

2023

Country
The CTBUH follows the United Nations's definition of Country, and thus uses the lists and codes established by that organization.

United States

City
The CTBUH follows the United Nations's definition of City, and thus uses the lists and codes established by that organization.

Boston

Function
A single-function tall building is defined as one where 85% or more of its usable floor area is dedicated to a single usage. Thus a building with 90% office floor area would be said to be an "office" building, irrespective of other minor functions it may also contain.

A mixed-use tall building contains two or more functions (or uses), where each of the functions occupy a significant proportion of the tower's total space. Support areas such as car parks and mechanical plant space do not constitute mixed-use functions. Functions are denoted on CTBUH "Tallest Building" lists in descending order, e.g., "hotel/office" indicates hotel function above office function.

Residential / Office

Structural Material
All-Steel
Both the main vertical/lateral structural elements and the floor spanning systems are constructed from steel. Note that a building of steel construction with a floor system of concrete planks or concrete slab on top of steel beams is still considered an “all-steel” structure as the concrete elements are not acting as the primary structure.

All-Concrete
Both the main vertical/lateral structural elements and the floor spanning systems are constructed from concrete which has been cast in place and utilizes steel reinforcement bars and/or steel reinforced concrete which has been precast as individual components and assembled together on-site.

All-Timber
Both the main vertical/lateral structural elements and the floor spanning systems are constructed from timber. An all-timber structure may include the use of localized non-timber connections between timber elements. Note that a building of timber construction with a floor system of concrete planks or concrete slab on top of timber beams is still considered an “all-timber” structure as the concrete elements are not acting as the primary structure.

Mixed-Structure
Utilizes distinct systems (e.g. all-steel, all-concrete, all-timber), one on top of the other. For example, a Steel Over Concrete indicates an all-steel structural system located on top of an all-concrete structural system, with the opposite true of Concrete Over Steel.

Composite
A combination of materials (e.g. steel, concrete, timber) are used together in the main structural elements. Examples include buildings which utilize: steel columns with a floor system of reinforced concrete beams; a steel frame system with a concrete core; concrete-encased steel columns; concrete-filled steel tubes; etc. Where known, the CTBUH database breaks out the materials used within a composite building’s primary structural elements.

Concrete Over Concrete-Steel Composite

Energy Label

Passive House Institute, WELL Gold, LEED Platinum targeted

Height
Architectural
Height is measured from the level of the lowest, significant, open-air, pedestrian entrance to the architectural top of the building, including spires, but not including antennae, signage, flag poles or other functional-technical equipment. This measurement is the most widely utilized and is employed to define the Council on Tall Buildings and Urban Habitat (CTBUH) rankings of the "World's Tallest Buildings."

210.5 m / 691 ft

To Tip
Height is measured from the level of the lowest, significant, open-air, pedestrian entrance to the highest point of the building, irrespective of material or function of the highest element (i.e., including antennae, flagpoles, signage and other functional-technical equipment).
210.5 m / 691 ft
Floors Above Ground
The number of floors above ground should include the ground floor level and be the number of main floors above ground, including any significant mezzanine floors and major mechanical plant floors. Mechanical mezzanines should not be included if they have a significantly smaller floor area than the major floors below. Similarly, mechanical penthouses or plant rooms protruding above the general roof area should not be counted. Note: CTBUH floor counts may differ from published accounts, as it is common in some regions of the world for certain floor levels not to be included (e.g., the level 4, 14, 24, etc. in Hong Kong).

48

Floors Below Ground
The number of floors below ground should include all major floors located below the ground floor level.

5

# of Apartments
Number of Apartments refers to the total number of residential units (including both rental units and condominiums) contained within a particular building.

317

Tower GFA
Tower GFA refers to the total gross floor area within the tower footprint, not including adjoining podiums, connected buildings or other towers within the development.

144,929 m² / 1,560,003 ft²

Structural Material Concrete Over Concrete-Steel Composite
Structural Details:
Bottom of Building
Columns
Reinforced Concrete
Columns
Steel
Core
Reinforced Concrete
Floor Spanning
Reinforced Concrete Floorplate
Floor Spanning
Steel Beam
Floor Spanning
Non-Structural Floor Topping
Top of Building
Columns
Reinforced Concrete
Core
Reinforced Concrete
Floor Spanning
Reinforced Concrete Floorplate

Rankings

#
1630
Tallest in the World
#
234
Tallest in North America
#
197
Tallest in United States
#
4
Tallest in Boston

Construction Schedule

2018

Proposed

2018

Construction Start

2023

Completed

Occupier/Tenant
Structural Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

MEP Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

WSP
Other Consultant

Other Consultant refers to other organizations which provided significant consultation services for a building project (e.g. wind consultants, environmental consultants, fire and life safety consultants, etc).

Property Management
Material Supplier

Material Supplier refers to organizations which supplied significant systems/materials for a building project (e.g. elevator suppliers, facade suppliers, etc).

Formwork
Developer
Millennium Partners
Occupier/Tenant
Cambridge Associates; Deloitte; McKinsey & Company
Architect
Design

Usually involved in the front end design, with a "typical" condition being that of a leadership role through either Schematic Design or Design Development, and then a monitoring role through the CD and CA phases.

Handel Architects LLP
Structural Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

MEP Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

WSP
Contractor
Main Contractor

The main contractor is the supervisory contractor of all construction work on a project, management of sub-contractors and vendors, etc. May be referred to as "Construction Manager," however, for consistency CTBUH uses the term "Main Contractor" exclusively.

Suffolk Construction Company, Inc.
Other Consultant

Other Consultant refers to other organizations which provided significant consultation services for a building project (e.g. wind consultants, environmental consultants, fire and life safety consultants, etc).

Façade

These are firms that consult on the design of a building's façade. May often be referred to as "Cladding," "Envelope," "Exterior Wall," or "Curtain Wall" Consultant, however, for consistency CTBUH uses the term "Façade Consultant" exclusively.

Socotec
Property Management
Sustainability
Steven Winters Associates
Material Supplier

Material Supplier refers to organizations which supplied significant systems/materials for a building project (e.g. elevator suppliers, facade suppliers, etc).

Formwork

Global News

25 August 2022

Boston Mixed-Use Building Built to Passive House Standards

Winthrop Center, a new 691-foot-tall (210.5-meter-tall) mixed-use tower in Boston was built to Passive House standards. The structure’s 812,000 square feet (75,437 square meters) of...

25 August 2022

Boston Mixed-Use Building Built to Passive House Standards

Winthrop Center, a new 691-foot-tall (210.5-meter-tall) mixed-use tower in Boston was built to Passive House standards. The structure’s 812,000 square feet (75,437 square meters) of...

24 October 2019

Planned Skyscraper Above Boston Rail Station Moves Forward

South Station Tower is planned to rise 677 feet (206.4 meters) above South Station, an aging transportation hub in Boston that’s swarmed daily by thousands...